Lesco New Connection

LESCO New Connection Procedure and Fees in Lahore

Getting a LESCO new connection in Lahore has become a much simpler and faster process thanks to the digital transformation introduced by the Lahore Electric Supply Company (LESCO). Whether you’re applying for a new electricity meter for your home, office, or business, understanding the correct procedure and estimated costs can save you both time and hassle. This guide provides an in-depth explanation of how to apply for a LESCO new connection, what documents you’ll need, and how much you can expect to pay in 2025.

Understanding LESCO and Its Role

LESCO (Lahore Electric Supply Company) operates under the Water and Power Development Authority (WAPDA) and supplies electricity to Lahore, Kasur, Sheikhupura, and Okara regions. The company manages billing, power distribution, maintenance, and new electricity connections. The LESCO new connection process is designed to ensure that consumers receive electricity safely and legally through verified installations.

Applying for a LESCO New Connection

The process of applying for a new connection can be completed online through the New Connection System (ENC), developed by the National Electric Power Regulatory Authority (NEPRA). This online platform streamlines the entire process—from form submission to installation tracking—so applicants don’t need to make unnecessary visits to LESCO offices.

Visit the ENC Portal

Start by visiting the official ENC website at https://enc.com.pk. This is the official platform used by all electricity distribution companies in Pakistan, including LESCO.

Fill Out the Application Form

Once on the ENC website, select “Apply for New Connection.” You’ll be prompted to fill in basic information such as:

  • Applicant’s full name
  • CNIC number
  • Contact details
  • Premises address
  • Type of connection (domestic, commercial, or industrial)
  • Load requirement in kilowatts

Make sure to provide accurate information, as discrepancies can delay your application approval.

Attach Required Documents

Applicants must upload scanned copies of the following documents along with their online form:

  • Copy of the applicant’s CNIC
  • Proof of ownership or tenancy (property document, rent agreement, or allotment letter)
  • Attested affidavit declaring that there’s no previous unpaid electricity connection at the premises
  • Site plan of the property (in some cases)
  • Neighbor’s reference number (optional but helpful)

These documents are reviewed by LESCO officials before the survey team visits your property.

Print and Sign the Application

After filling out the form and uploading documents, download the completed application form. Sign it and attach your CNIC copy before submitting it to your respective LESCO subdivision office or upload it online through the ENC portal.

Site Inspection

A LESCO survey team will visit your premises to verify the details provided in your application. They check wiring, load requirements, and the feasibility of supplying electricity to the location. If everything meets safety standards, your application moves to the next phase.

Payment of Demand Notice

Once the site inspection is approved, you’ll receive a Demand Notice (DN)—an official LESCO document that includes your connection charges. The DN must be paid at an authorized bank branch. Keep the payment receipt safe, as it will be required for verification.

Meter Installation

After the payment is verified, LESCO schedules your meter installation. Typically, the new connection is provided within 20–25 working days after the Demand Notice is cleared.

LESCO New Connection Fees in Lahore

The fees for a LESCO new connection vary depending on the connection type and load capacity. LESCO follows the NEPRA-approved tariff structure, which ensures transparency for all consumers.

Residential Connection Fees

For domestic users, the charges generally include:

  • Application processing fee
  • Service connection charges
  • Security deposit (based on connected load)
  • Cost of meter and installation

As of 2025, the estimated cost for a single-phase domestic connection ranges from Rs. 10,000 to Rs. 20,000, depending on load requirements. Three-phase or higher-load residential connections may cost between Rs. 25,000 and Rs. 40,000.

Commercial and Industrial Connection Fees

Commercial and industrial connections involve higher service charges and security deposits because of larger power demands.

  • Commercial connections: Rs. 30,000 to Rs. 80,000 (approx.)
  • Industrial connections: Rs. 100,000 and above, depending on sanctioned load

Keep in mind that these costs may vary based on the applicant’s location, wiring distance from the main transformer, and material requirements.

Tracking the LESCO New Connection Status

You can track your LESCO new connection status anytime via the ENC portal. Simply visit the website, click on “Track Application,” and enter your application number or CNIC. The portal provides real-time updates such as “Application Received,” “Survey Completed,” “Demand Notice Issued,” and “Meter Installed.”

This transparency helps applicants avoid unnecessary visits and stay informed about every stage of the process.

Common Issues and How to Avoid Delays

Sometimes, applications for new connections face delays. Here’s how to prevent them:

  • Double-check all uploaded documents for clarity and validity.
  • Make sure the property’s wiring meets safety standards.
  • Pay the Demand Notice promptly.
  • Avoid providing incorrect load details.

If delays still occur, you can contact the LESCO Helpline (111-000-118) or visit your nearest LESCO subdivision office.

LESCO New Connection for Tenants

Tenants can also apply for a new meter if the property owner provides written permission. The owner’s CNIC copy, an affidavit, and a valid rent agreement must be included in the documents. LESCO treats tenant applications with the same procedure as ownership-based ones, provided the required legal documentation is complete.

Online Bill Management After Getting a New Connection

Once your new meter is installed, you’ll begin receiving monthly bills based on your electricity consumption. To stay updated, you can easily track and download your bill online using the Lesco Online Bill Check feature. This service allows you to enter your 14-digit reference number and instantly view your current bill, payment status, and due date.

You can also use Online Bill Check for other distribution companies across Pakistan, making it convenient to manage multiple connections or commercial properties.

Benefits of Applying Online for LESCO New Connection

The ENC system provides several advantages over manual applications:

  • No need to stand in long queues at LESCO offices.
  • 24/7 online submission and tracking.
  • Transparent process with minimal paperwork.
  • SMS updates for important stages like survey approval and meter installation.

This digital system ensures that applicants have a hassle-free experience from start to finish.

Estimated Time for LESCO New Connection

The complete LESCO new connection process usually takes 20 to 45 days. However, this depends on:

  • Application completeness
  • Site feasibility and inspection results
  • Prompt payment of the Demand Notice
  • Availability of meters and technical staff

Timely communication with LESCO and proper documentation can significantly speed up the process.

Getting a LESCO new connection in Lahore has never been easier. With the ENC online system, applicants can submit forms, upload documents, and track their application—all from the comfort of home. Whether you’re a homeowner, tenant, or business owner, following the correct procedure ensures a quick and hassle-free experience.

Once your connection is live, remember to regularly monitor your electricity bills using the Lesco Online Bill Check tool. This not only helps you stay updated on payments but also ensures transparency in your energy usage.

FAQs

1. How can I apply for a LESCO new connection online?

You can apply online through the official ENC portal at https://enc.com.pk by filling out the form and uploading required documents.

2. What documents are required for a new LESCO connection?

CNIC copy, property ownership proof, affidavit, and sometimes a site plan are mandatory documents.

3. How long does it take to get a new electricity connection from LESCO?

Typically, it takes between 20 and 45 working days, depending on the area and application type.

4. What is a Demand Notice in the LESCO connection process?

A Demand Notice is the official payment slip issued by LESCO after site approval. It must be paid before installation.

5. Can tenants apply for a new LESCO meter?

Yes, tenants can apply if they have the property owner’s permission, CNIC, and a verified rent agreement.

6. How much does a new domestic connection cost?

A single-phase domestic connection generally costs between Rs. 10,000 and Rs. 20,000 in 2025.

7. How can I check my new connection status?

Visit the ENC portal and click “Track Application” to see your progress.